Al Quoz, Dubai — G+4 · 8,200 sqm

Government Facility, Al Quoz
ValueAED 96M
Programme16 months
DeliveryDesign+Build
Year2023
Project Overview

A DisciplinedDelivery.

ClientFederal Government Authority
StatusCompleted · Handed Over Q4 2023

A compliance-first institutional facility delivered under a single design-and-build contract, combining secure administrative floors, public-facing service halls and specialist data infrastructure to federal government standards.

The Challenge

Stringent security clearances, fixed authority milestones, and a public-facing programme that demanded zero compromise on accessibility, life-safety and document-controlled handover.

GoTech's Solution

GoTech mobilised a vetted delivery team, ran early authority engagement, and self-performed civil, structural and MEP packages to hold the 16-month programme without claim or extension.

Project Highlights

What We Delivered.

01

Secure Frame & Envelope

Hardened reinforced concrete structure with blast-rated glazing to public elevations.

02

Resilient MEP

N+1 power, redundant cooling and structured cabling for a Tier-rated server suite.

03

Public Service Halls

Double-height accessible service zones with controlled circulation and queueing systems.

04

Document-Controlled Handover

Full O&M, asset register and as-builts delivered under a federal QA protocol.

Scope of Works

Integrated Delivery.

▸

Reinforced concrete superstructure to G+4

▸

Blast-rated façade & secure envelope

▸

Tier-rated data & server infrastructure

▸

Full MEP with N+1 resilience

▸

Public-realm & external works

▸

Authority NOCs & federal handover

At a Glance
8.2KGFA (sqm)
16Months Programme
96MProject Value (AED, demo)
Next Step